MMP706: Project Management Assignment, AeU, Malaysia You are the project manager for your company’s MCP project. You are collaborating with your project team and business
University | Asia e University (AeU) |
Subject | MMP706: Project Management |
QUESTION 1
You are the project manager for your company’s MCP project. You are collaborating with your project team and business analyst to choose the most effective method for gathering requirements from project stakeholders. The stakeholders for this project are spread across West Africa, but you want to include everyone in the requirements-gathering process. There is some concern that, because your group is so dispersed, it will be difficult to gather the required information effectively.
- Complete the following table to identify the characteristics of each technique and how it may, or may not, be helpful in this project.
- You want the stakeholders to vote on the main project needs because your stakeholder group is so big. Even if there isn’t a majority in favor of the requirements you choose, you’ll still utilize the plurality approach to rank them in order of importance. Describe in detail what is the plurality method and how risky is it for project requirements.
- You are now prepared to build the requirements management strategy now that the MCP project has established the project’s needs. The project requirements will be managed as part of the project according to the requirements management plan. What component of the requirements management plan is responsible for recording and why is this component needed in maintaining control over the physical attributes of the project’s product?
QUESTION 2
The MindGineer Project for your organization has been assigned to you to oversee as the project manager. A completion budget of RM 1,500,000 and an 18-month timeline are set forth for this project. The project has been ongoing for some time, and it is currently 30% finished, even though you were expected to guarantee 35% completion at this point. Your project continued to be delayed and has already cost RM 485,230 as a result of unforeseen mistakes.
- Given the above information, complete the following table of earned value
management formulas:
- Another project manager who has been assisting you has created an optimistic estimate of RM 10,450, a most likely estimate of RM 22,300, and a pessimistic estimate of RM 36,650 for a portion of this project. What is the three-point estimate in this scenario?
- You are currently assisting Datuk Darryl, the project manager for your client, in setting up the project management process for this project. Draw the project management life cycle components for Datuk Darryl to recognize the entire project flow.
Get Help By Expert
Struggling with your MMP706 project management assignment? Look no further! Assignment Helper MY offers a reliable 'do my assignment' service that ensures your academic success. Our Malaysian assignment experts team is committed to delivering unique and well-researched solutions within your deadline. Trust us to handle your project management assignment and experience the difference today.
Recent Solved Questions
- Capital Budgeting Assignment : PIONG Corporation Case Study for NPV, IRR & Risk Analysis
- Business Intelligence and Analytics Systems Assignment, TU, Malaysia Find recent cases of successful text mining and Web mining applications. Visit the websites of some text
- MPU3193: Philosophy and Current Issues Assignment, WOU, Malaysia After 64 years of being an independent country, do you think that Malaysia is free from the influence of Western colonization
- BAC305: White Inc is a wholly 100% subsidiary to Malaysian company, Black Bhd: Company Accounting Reporting Assignment, WOU, Malaysia
- Introduction to Statistic Assignment, UiTM, Malaysia Sabah Electricity Sdn Bhd in Kota Kinabalu is conducting a survey to find out the average monthly consumption of electricity
- BAC10204 Assignment 2: Business Report and Presentation Management & Science University
- FBF1163 Fundamentals of Programming Assignment, UCSI, Malaysia Presume that your class at UCSI finishes at 6:30 pm and you must travel 6 km to reach your home for dinner
- BED15203: Write a C program that prompts a user to enter 3 integer numbers. The program then determine: Fundamentals of Programming Assignment, UniKL, Malaysia
- LAW 437: Constitutional law Assignment, UTM, Malaysia Discuss critically the constitutional impact and significance of the following decided cases with special emphasis on the freedom of speech and expression
- HPGD1103: What impact do you think new technologies are having on the way curricula are developed and delivered?: Curriculum Development Assignment, Malaysia