CCM Level 5 Performance Assessment PMP Sample
For information and reference only – not to be submitted as your own work.
This CCM performance assessment sample shows how selected sections of a Project Management Plan (PMP) can be written for the MRSM Merbok design-and-build case, where the candidate acts as Construction Manager for the main contractor. It follows the original Level 5 question page. For a planning method behind it, read our guide on how to write the CIDB CCM performance assessment PMP.
The extract covers only part of the full 5,000–8,000-word PMP. Every cost, percentage and delay figure that is not taken from the brief is labelled illustrative and must be replaced by your own site data.
What this sample covers
| Brief requirement | Where answered in this extract |
|---|---|
| Expand the given assumptions and add new ones | Assumptions register |
| Project baselines (time, cost, scope) | Project baseline and key dates; WBS and milestones |
| Modules 1–3: fundamentals, tendering, site mobilisation | Assumptions register; Site mobilisation plan |
| Modules 4–5: planning and cash flow | WBS and milestones; Cash flow and S-curve |
| Modules 6–8: quality, safety, environment | Quality, safety and environment controls |
| Module 15: contract administration (LAD) | LAD exposure calculation |
| Module 17: handover | Handover and defects liability period |
| Modules 9–14 and 16 (materials, labour, subcontractors, plant, site office, stakeholders) | Not expanded here; each needs its own section in the full PMP |
Model answer extract
1. Assumptions register
A PMP rests on stated assumptions, because baselines are only as reliable as the conditions they assume (PMI, 2021). The register below keeps the brief’s given facts separate from the candidate’s added assumptions, so an assessor can see what was supplied and what was reasoned.
| Ref | Assumption | Source | Impact if wrong |
|---|---|---|---|
| A1 | Contract sum is RM 40,500,000.00 under a design-and-build arrangement with MARA | Given | Cost baseline invalid |
| A2 | Site possession on 6 March 2021; 104 weeks; completion on 5 March 2023 | Given | Programme baseline invalid |
| A3 | LAD at RM 12,031.00 per day; defects liability period of 36 months | Given | Delay and handover exposure misstated |
| A4 | Employer’s requirements and design brief are frozen after design sign-off, with no major change in scope | Added | Redesign delays piling and structure |
| A5 | Authority approvals (building plans, utility connections) are obtained within the periods allowed in the master programme | Added | Delay not excusable unless the contract grants an extension |
| A6 | Skilled labour and key materials are available locally in the northern region at stable prices | Added | Cost escalation and slow progress |
| A7 | Seasonal rainfall is allowed for through a weather allowance in the programme (illustrative: 8% of external-work days) | Added, illustrative | Earthworks and external works slip |
| A8 | Subcontractors are nominated or appointed before the start of their packages, with approved method statements | Added | Interface clashes and rework |
Each added assumption is paired with a trigger. For A5, for example, the Construction Manager reviews approval status at every fortnightly progress meeting and escalates to the project director if a submission is more than 14 days (illustrative) behind plan.
2. Project baseline and key dates
The time baseline is anchored to the possession date. Counting 104 weeks (728 days) from Saturday 6 March 2021 gives Saturday 4 March 2023, while the brief states completion on 5 March 2023, which is 729 days after possession. The one-day difference is common when a contract counts the possession day as day one. The PMP therefore adopts 5 March 2023 as the contractual date and records the counting convention as an assumption to confirm against the contract’s appendix.
| Baseline item | Value | Basis |
|---|---|---|
| Site possession | 6 March 2021 | Given |
| Contract period | 104 weeks | Given |
| Date for completion | 5 March 2023 (a Sunday) | Given; 729 days after possession |
| Week 52 (half-way) | 5 March 2022 | Calculated: 6 March 2021 plus 364 days |
| Contract sum | RM 40,500,000.00 | Given |
| Defects liability period | 36 months from practical completion | Given |
| Defects liability period end if completion is on time | On or about 5 March 2026 | Calculated |
3. Work breakdown structure and key milestones
The scope is divided by building group, since administrative, academic, student facility, residential and support buildings can proceed in parallel once enabling works are complete. Following the work-breakdown approach described by Harris, McCaffer and Edum-Fotwe (2013), each package has a single responsible manager. The week numbers below are illustrative and would be derived from the master programme.
| WBS | Package | Illustrative milestone | Illustrative week |
|---|---|---|---|
| 1 | Mobilisation, site clearing and earthworks | Platforms formed | 12 |
| 2 | Roads, parking and drainage (primary network) | Temporary access and main drains in place | 20 |
| 3 | Substructure and piling, all building groups | Foundations complete | 32 |
| 4 | Superstructure (frames, floors, roofs) | Roofs watertight | 60 |
| 5 | Architectural finishes and mechanical and electrical services | Testing and commissioning begins | 86 |
| 6 | External works, landscaping and final roads | Final surfacing | 96 |
| 7 | Inspection, authority approvals and handover | Certificate of completion application | 102 |
4. Site mobilisation plan
Mobilisation in the first four weeks (up to 3 April 2021) establishes control before production begins. The sequence is: site boundary, security and temporary fencing; main access and wheel-washing point; site offices and a clerk-of-works room for the employer’s representative; temporary power and water; storage and fabrication yards; and welfare facilities sized to the peak labour force. Layout is planned so that heavy plant routes do not cross pedestrian paths, and material stacking sits close to the first building groups to be started.
Insurance, performance security and permits are lodged before the first excavation. The Construction Manager also issues a mobilisation checklist, signed off by the site agent, safety officer and quantity surveyor, so that no work package starts without its resources confirmed.
5. Cash flow and S-curve logic
The cash-flow forecast converts the programme into expected valuations. Because progress is slow at start-up, fast during structure and slows during finishing and commissioning, cumulative value traces an S shape. The figures below are illustrative only: they spread the RM 40.5 million contract sum across eight quarters of the 104-week period and ignore retention, advance payment and price adjustment.
| Quarter (13 weeks each) | Illustrative share of contract sum | Illustrative value (RM million) | Illustrative cumulative (RM million) |
|---|---|---|---|
| Q1 | 3% | 1.22 | 1.22 |
| Q2 | 7% | 2.83 | 4.05 |
| Q3 | 12% | 4.86 | 8.91 |
| Q4 | 18% | 7.29 | 16.20 |
| Q5 | 20% | 8.10 | 24.30 |
| Q6 | 18% | 7.29 | 31.59 |
| Q7 | 14% | 5.67 | 37.26 |
| Q8 | 8% | 3.24 | 40.50 |
Actual cumulative value is plotted against this baseline each month. A gap of more than 5% (illustrative threshold) triggers a recovery plan and a review of subcontractor payments, since the contractor funds work between valuation and payment.
Struggling to turn 17 modules into one coherent plan? Our management assignment help team can review structure, baselines and tables with you.
6. Quality, safety and environment controls
Quality. The quality plan sets inspection and test plans for each trade, hold points before concealment, and a defects register closed out weekly. Workmanship is checked against the CIDB Quality Assessment System in Construction (QLASSIC), which CIDB publishes as Construction Industry Standard CIS 7 (CIDB, 2014). Target scores should be set in the plan and agreed with the employer. The management system is aligned with ISO 9001 principles of documented processes and corrective action.
Safety. The Occupational Safety and Health Act 1994 places duties on employers to provide a safe system of work (Malaysia, 1994). The Occupational Safety and Health (Amendment) Act 2022 came into force on 1 June 2024 (Malay Mail, 2024), after this project’s 2021–2023 period, so the plan should state which legal position applied during construction and avoid presenting later duties as binding retrospectively. Site controls include toolbox talks, permit-to-work for height and excavation, scaffold inspection, and an incident log reviewed at progress meetings.
Environment. The Environmental Quality Act 1974 is the framework statute (Malaysia, 1974). The plan should check whether any part of the works falls within the prescribed activities requiring an Environmental Impact Assessment, and in any case control silt, dust, noise and waste through sediment traps, covered stockpiles, restricted working hours and a scheduled-waste procedure.
7. LAD exposure calculation
Liquidated and ascertained damages are the employer’s pre-agreed compensation for late completion. With LAD at RM 12,031.00 per day, exposure grows linearly with delay. The scenarios below are illustrative delays, not forecasts, and assume no extension of time is granted.
| Illustrative delay (days) | Calculation | LAD exposure (RM) | Illustrative revised completion |
|---|---|---|---|
| 30 | 12,031 × 30 | 360,930.00 | 4 April 2023 |
| 45 | 12,031 × 45 | 541,395.00 | 19 April 2023 |
| 60 | 12,031 × 60 | 721,860.00 | 4 May 2023 |
The daily rate equals about 0.03% of the contract sum (12,031 ÷ 40,500,000). The Construction Manager’s controls therefore include early notice of delay events, contemporaneous records for any extension-of-time claim, and acceleration options priced against the daily LAD figure (Harris, McCaffer and Edum-Fotwe, 2013).
8. Handover and defects liability period
Handover starts well before the date for completion. From about week 96 the plan schedules pre-completion inspections by building group, commissioning of services, as-built drawings, operation and maintenance manuals, and training for the employer’s maintenance staff. A punch list is closed out before the certificate of completion is requested.
During the 36-month defects liability period the contractor keeps a response team and a defects log with agreed response times. If practical completion is certified on 5 March 2023, the period would run to about 5 March 2026; any delay moves this date. The plan ends with a lessons-learned review and a final account.
Want a second pair of eyes before you submit? Have your references checked through our citation and referencing verification service, or submit your assignment brief for a quote.
References
- CIDB Malaysia (2014) Construction Industry Standard CIS 7: Quality Assessment System for Building Construction Works (QLASSIC). Kuala Lumpur: Construction Industry Development Board Malaysia. Available at: https://smart.cidb.gov.my/program/qlassic
- Harris, F., McCaffer, R. and Edum-Fotwe, F. (2013) Modern Construction Management. 7th edn. Chichester: Wiley-Blackwell.
- Malay Mail (2024) Human Resources Ministry: Amended Occupational Safety and Health Act to come into force on June 1, 4 April. Available at: https://www.malaymail.com/news/malaysia/2024/04/04/human-resources-ministry-amended-occupational-safety-and-health-act-to-come-into-force-on-june-1/127335
- Malaysia (1974) Environmental Quality Act 1974 (Act 127). Kuala Lumpur: Government of Malaysia.
- Malaysia (1994) Occupational Safety and Health Act 1994 (Act 514). Kuala Lumpur: Government of Malaysia.
- Project Management Institute (2021) A Guide to the Project Management Body of Knowledge (PMBOK Guide). 7th edn. Newtown Square, PA: Project Management Institute.
Prepared by
Assignment Helper Editorial Team
This model answer was prepared by our editorial team in response to a real assignment brief we received. It shows one way to approach the task and is meant as a study guide, not for submission.
Need a custom answer for your subject?
Share your module details and get fast, original academic support from our team.